AMP6 - CSO/Pumping Station
During AMP6 the team constructed & refurbished several pumping stations & Combined Sewer Overflows(CSO's). These included work on some key assets within the Welsh Water portfolio to ensure they performed as required to meet regulatory requirements. Survey information gathered & collated during both the CSO verification project & the Event Duration Monitoring (EDM) installation project informed the design teams and enabled tailored cost-effective solutions to be developed. A mixture of in-situ & off-site pre-packaged construction methods were used to optimise the construction phase.
AMP7 - CSO/Pumping Station
The work started in AMP6 will continue during AMP7, with a focus on reducing costs using innovation through the design & construction process
HoTV SPS
HoTV SPS
HoTV SPS
HoTV SPS